Concrete Calculator
Calculate volume, bags, weight and cost for any concrete shape.
► Calculation details
Estimates only. Confirm with your supplier or engineer before ordering.
Enter your dimensions, then press Calculate.
Calculate volume, bags, weight and cost for any concrete shape.
Estimates only. Confirm with your supplier or engineer before ordering.
Enter your dimensions, then press Calculate.
Every concrete estimate starts with volume. The core formula is simple: Volume = Length × Width × Thickness. The challenge lies in unit discipline. Mixing feet and inches without converting first is the most common source of error. This calculator handles all conversions for you, but if you are working by hand, convert all dimensions to the same unit before multiplying.
Once you have volume in cubic feet, divide by 27 to get cubic yards — the unit most suppliers quote. Multiply cubic yards by 0.7646 to get cubic meters.
Volume = Length × Width × Thickness
Volume = (Length × Height − openings area) × Thickness
Volume = π × r² × Height (r = diameter ÷ 2)
Each step adds a rectangular block of concrete equal to its width × tread depth × riser height. The staircase volume is the sum of all steps, building from the bottom up (step 1 = 1 riser, step 2 = 2 risers, etc.).
Volume = (Curb cross-section area + Gutter cross-section area) × Run length, where curb cross-section = curb width × curb height and gutter cross-section = gutter width × gutter thickness.
Pre-mixed bags are ideal for volumes below roughly one cubic yard (27 ft³). They are available at any hardware store, and no minimum order applies. Ready-mix concrete is delivered by truck and becomes economical above one yard because delivery charges and minimum loads (usually 1 yd³) offset the higher per-unit bag cost.
| Bag size | Yield per bag | Bags per yd³ |
|---|---|---|
| 40 lb | 0.30 ft³ | 90 bags |
| 50 lb | 0.375 ft³ | 72 bags |
| 60 lb | 0.45 ft³ | 60 bags |
| 80 lb | 0.60 ft³ | 45 bags |
The most common general-purpose mix is 1:2:3 — one part Portland cement, two parts sand and three parts coarse aggregate by volume. By weight this corresponds to roughly 22% cement, 33% sand and 45% aggregate of the total concrete volume. A higher cement ratio (such as 1:1.5:3) produces stronger concrete suitable for structural members, while a lean mix (1:3:6) is used for mass fills where high strength is not required.
Normal-weight concrete weighs approximately 150 lb per cubic foot, which is 4,050 lb (about 2 short tons or 1,837 kg) per cubic yard. Reinforced concrete with embedded rebar typically runs 155–160 lb/ft³. Lightweight concrete — made with expanded shale or pumice aggregate — weighs 90–115 lb/ft³ and is used where dead load must be minimised.
Even the most careful pour loses material to spills, uneven sub-base, overfill at form edges and volume rounding. Industry practice is to order 5–10% more than the calculated volume. Increase this to 10–15% if the ground surface is rough or uneven. Running short mid-pour is far more costly and disruptive than having a little left over, since a cold joint weakens the finished slab.
Thickness is the single biggest driver of concrete volume. Use these guidelines as a starting point:
Curing is the process of maintaining moisture and temperature in fresh concrete so it reaches its design strength. The strength gain schedule for a standard mix is roughly:
Keep the surface moist by covering with wet burlap or a plastic sheet, especially in hot or windy conditions. Avoid placing concrete below 4°C (40°F) without cold-weather precautions.
1 yd³ = 27 ft³
1 m³ = 1.308 yd³
1 yd³ = 0.7646 m³
Normal weight = 150 lb/ft³
60-lb bag = 0.45 ft³ = 60 bags/yd³
Waste = add 5–10%